Building Erection Techniques

Building Erection Techniques

Any metal building system, no matter how well designed, may become a continuous source of problems if installed incorrectly. Erection of metal buildings is a specialized field in which the builder’s success depends on years of experience with a particular system or manufacturer. There is no single perfect way to construct a metal building, even in theory, as various manufacturers suggest slightly different methods of assembly, and erection techniques of various crews differ.

 

It is important that the customer selects an experienced and approved building contractor for erection of his building.

Anchor bolts should be installed only as per the “Issued for Construction” Anchor Bolt Setting Plan Only, and strict adherence to this drawing is required when placing anchor bolts prior to pouring of concrete for pedestals.

Note: Never use Approval Drawings of Anchor Bolt Setting Plan for setting anchor bolts.

 
 

Material Storage

Upon delivery, the erection team should inspect the shipment. If the inspection discovers that packaged or nested metal components have become wet in transit, the erection team is expected to unpack and dry them out to prevent rusting.

Experienced erectors store the building components in a logical way which helps, rather than hinders, future erection. They also plan the erection process beforehand and know when each building part is needed.

 
Building Erection Techniques

Building components must be stored in accordance with MBS‘s instructions.

  • Roofing and siding panels are normally kept in a slightly sloped position for drainage,
  • Cold-formed girts and purlins may be stored flat, to eliminate hard points at the supports.
  • Proper dunnage keeps the metal members off the ground rather than allowing them to sink into the mud.
  • Rolls of fiberglass insulation are best kept off the ground and covered.

MBS is not involved in the actual construction. MBS strongly recommends experienced Erection teams to erect the building directly. MBS will provide technical support when needed during the process of steel assembly. The Erector is solely responsible for the means, methods, techniques, and sequences of construction. The erector should ensure that erection is in conjunction with the erection drawings provided for the project.

 
 
Building Erection Techniques

Main Frame Erection

Erection shall begin with the erection of braced bays, these braced bays provide support for the other members during erection. Whichever installation method is preferred by the erector, they should incorporate proper erection bracing, which may be more substantial than the permanent bracing of the building. Note the MBMA Common Industry Practices.

“Bracing furnished by the Manufacturer for the Metal Building System cannot be assumed to be adequate during erection.” Inadequately braced metal buildings have been known to collapse during erection.

Installation of Girts and Purlins

Some girts and purlins necessary for bracing are installed along with the main frame, and the remainder are put in place immediately thereafter. Girts and purlins may be bolted directly to the main frame steel or can be attached to it via bearing clips pre-welded to the frame, (as supplied by MBS).

It is often more cost-effective to raise the purlins onto the roof in bundles rather than one by one. The bundles are placed near the eaves, from where the erectors can move the individual purlins to their intended positions by hand. Purlin bracing should be set in place as soon as possible and definitely before the roofing is installed.

 

Placement of Insulation

Insulation is placed after the secondary steel is installed, but before the cladding. In buildings with fiberglass insulation under through-fastened roofing, the roofing is attached to purlins right through the insulation. MBS recommends letting the roof insulation overhang the framing edge, removing about 150 mm of fiberglass from its facing, and then folding the facing back over the insulation to prevent wicking of moisture.

 
Installation of Girts and Purlins

The attachment of roof blanket insulation is a hazardous job, because no roofing is yet installed to support the workers in case of a fall. Adequate safety arrangement should therefore be made.

Installation of Roof and Wall Panels

Whether roof or wall panels are installed first, is a matter of the erector’s preference. We favor erecting the roof first to allow for any interior finishing work to begin and to improve the roof diaphragm action in the partially constructed building.

Installation of roof panels usually starts at one of the end walls chosen to allow for panel placement in the direction opposite to the prevailing winds; this sequence is intended to decrease the chances of wind-blown water intrusion into the panel side-laps.

Stepping on the panel ribs is strongly discouraged by the manufacturers, as is walking on partially attached or unattached panels. The safe way to walk on a fully fastened roof is to step on walk boards laid in the panels’ flat areas and spanning between the purlins.

To prevent slippage, the walk boards should be secured to the roofing. If stepping on the panels is unavoidable, one should attempt to walk directly above the purlins where possible and to stay away from the middle of the flat panel part. Wall panels are installed similar to roof panels.

Need help or have a question?

UAE:
+971508692438
INDIA:
+919825164743
Established in 2004,DASHPROJECTS , is one of the business units of DASH GROUP, having a large production capacity, with expertise in the field of manufacturing, site construction and heavy lift.
DASHPROJECTS has world-class design capabilities emanating from a rich pool of highly qualified and experienced team of design engineers combined with cutting edge technologies and an unparalleled
Construction is the process of constructing a building or infrastructure. Construction differs from manufacturing in that manufacturing typically involves mass production of similar items without a
Our Construction Project Management services are designed to improve and control the cost and schedule of a project for the Owner’s benefit. We represent the interests of Owners and Developers
Instrumentation and Control plays a significant role in both gathering information from the field and changing the field parameters, and as such is a key part of control loops. The Instrumentation
DASH Central Engineering Department is located in UAE  Our engineering department is composed of 2 sections; Steel Design section & Steel Detailing section. DASH engineering is
In DASHPROJECTS (DASH), the project management team, selected and led by the project manager, is responsible for coordinating and integrating activities across multiple functional lines: A-The
DASHPROJECTS (DASH) owns several factories to fabricate structural steel, Pre-engineered Buildings and material handling systems. These factories are located in Egypt, Syria and UAE . Our factories
Erection / installation of the company’s projects are implemented by developing the erection method statement considering the complexity of the Job, project schedule, site logistics,
Pre-engineered steel buildings can be fitted with different structural accessories including mezzanine floors, canopies, fascia, interior partitions etc. and the building is made water proof by use
Roots Steel International Structural Steel business unit had executed different categories of projects such as Industrial buildings, Airports terminals, Airport Hangers, warehouses, sport
Structural steel and plate construction associated with crusher plants, cement factories, batching plants, block factories and sorting plants to be used as rock box hoppers, silos, chutes, conveyors
DASHPROJECTS Pre-Engineered Steel Buildings (PEB) The main components of a PEB are built up at the plant with strict adherence to the carefully engineered design and according to the
For a comparison of Pre Engineered Steel Buildings and Conventional Steel Buildings, please click on the below image:     PEB vs
DASHPROJECTS  produces sandwich panels in 6 thicknesses: 35 mm, 50 mm, 75 mm, 100 mm, 125 mm and 150 mm, with an excellent slip joint connection for structural strength and weather
The structural steel division at DASHPROJECTS has the capability and capacity to supply structural steel buildings for selected types of projects, including (but not limited to): Desalination
At MBS, our commitment is to always provide: The fastest response to a request for quotation The most competitive prices Proposal drawings to help visualize your building
Frames in PEB are mainly rigid frames – comprise of Taper Columns & Rafters, are built using the state of art technology. Splices plates are welded to the ends of the tapered
SSIPL HI-RIB Sheet Profile Metals panels are the most attractive features of Metal Building System, having contributed mightily for the growing popularity of the Metal Buildings. The term
SSIPL Standing Seam Roof System - SSR 600 Standing Seam blends the aesthetics of an architectural panel with the strength of a structural panel. These panels have a good uplifts ratings assuring
Insulated Roof and wall Cladding Heating or cooling is one of the largest operating expense in a building. That's why it is important that each building has good thermal insulation adapted for
When Crane System is required, SSIPL supply includes Columns, Rafters, Brackets, Crane runway beams & lateral tie that support crane system. Clients have to provide complete crane data
The standard mezzanine framing system consists of a steel deck support by joists into main mezzanine beams. If required by design loads, the main beams shall also be supported by
Single Flight Staircase Elevation: Single Flight Staircase with Mid-Landing Plan: Single Flight Staircase with Mid-Landing Double Flight Staircase
Isometric : Curved Eaves Roof Extension at Eave (without Soffit) Roof Extension at Eave (with Soffit) Canopy with Curved Eaves with Bottom
        Fascia System   Flush Fascias with Eave Gutter Typical Sidewall Section forFlush FasciaTypical Endwall Section forFlush Fascia
Jack Beams are used to make economical as well as safe approach for creating longer bay length when large unobstructed space, is required. Common bay lengths (5,6,7,8,9 & 10) can be
Ridgevent System S-Type Louver Detail Roof Monitor Turbovent Fixing Detail Gutter / Downspout Fixing To Wallpanel Using
The basic parameters that define a pre-engineered building are: Building width, Building length, Building height, Roof slope, End bay length, Interior bay length and Design loads. Width : No
Dash Projects pre-engineered buildings are custom-designed to meet your exact requirements. The most common Primary Framing systems are shown below. Practically any frame geometry is possible.
Purlins, girts and eave struts are secondary structural members used to support the wall and roof panels. Purlins are used on the roof; girts are used on the walls and eave struts are used at the
Nearly 70% of all single storey non-residential construction now utilizes preengineered buildings. Applications range from small car parking sheds to 90 m (+), wide clear span aircraft hangars to
DashProjects offers a complete line of Wall/Roof panels, panel related accessories, trims, purlins, girt, eave gutters, downspouts, curved eaves, wall flashings and louvers for a wide range of
The panels used in the construction of DashProjects Pre-Engineered Buildings are composed of the following: Base metal of either Galvalume coated steel conforming to ASTM A 792M Grade 345B or
Liner panels have one metal skin surface with polystyrene foam board adhered to it for better insulation. In the past 20 years, end-users, contractors and consultants have become increasingly aware
Drawings DASHPROJECTS produces its own shop drawings for the fabrication of your steel joists, trusses, structural steel components, steel deck and girts. For project design, bid preparation or
Open web steel joist (OWSJ) is a lightweight steel truss consisting, in the standard form, of parallel chords and a triangulated web system, proportioned to span between bearing points. The main use
 Steel deck is a cold formed corrugated steel sheet supported by steel joists or beams. It is used to support concrete or insulating membrane of a roof. Zamil steel decks are based on load
Combining DASH PROJECTS joists with poured concrete, the system consists of hybrid concrete/steel T-beams running in one direction and an integrated continuous slab in the other (see drawing below).
With more than 45 years of hands-on experience related to the value implications of design our early involvement in the project is fundamental for the management of the entire structural steel
At DASH PROJECTS, we endeavour to ensure our employees’ skills and our production systems and equipment are constantly aligned to international standards. Our production efforts are driven by
With more than 14,000 m2 covered paint shop, an open yard paint shop of 5,000 m2 at our facility in UAE and leading-edge CNC blasting machines, our ability to deliver both quantity and quality
INSULATION The main purpose of insulating a building is to reduce the heat transfer coming through the ceilings and openings. Polyurethane Insulation This is a panel manufactured by the
Steel exhibits desirable physical properties that make it one of the most versatile structural materials. Some of its properties such as strength, uniformity, light weight, ease of use, etc., make it